Introduction to Downtown Streetscape Project Visual Update August 13 2010
Exploring Downtown Streetscape Project Visual Update August 13 2010 reveals several interesting facts. The finishing touches are now being down on E. Magnolia Avenue and work continues on S. Eustis Street.
Downtown Streetscape Project Visual Update August 13 2010 Comprehensive Overview
Phase IV has begun on the homestretch of the Work has started on Eustis Street, north of Magnolia, with the removal of the oaks. Work continues on Eustis Street (north of Magnolia Avenue).
Work continues on the north side of Eustis Street with the forming of the sidewalks and getting ready to install the pavers.
Summary & Highlights for Downtown Streetscape Project Visual Update August 13 2010
- Here's a weekly glimpse of the progress of the
- Paver installation is wrapping up on Eustis Street and demolition of Magnolia between Grove and Eustis Street is underway.
- "The pieces are all coming together" - work continues on Magnolia (between Bay and Eustis Streets).
- Work continues on Eustis Street north of Magnolia and is progressing toward the intersection of Eustis and Magnolia.
- Work continues on East Magnolia Avenue and the Demolition has begun on South Eustis Street.
Stay tuned for more updates related to Downtown Streetscape Project Visual Update August 13 2010.